Microsoft Project start date

Project 2007 – Software

1.  I have set a start date and have created an entire schedule, I now need to move the start date and keep the same sequences, but not all things are linked together – how do i do this?

2.  Multiple times this may occur throughtout the project. If my project is delayed by weather, inspectors, suppliers, etc and I need to move it to tomorrow and have everything after move in the same sequence – when things may not be linked together – how do I do that?